Electricity Connections
Get your new electricity connection in the UK with ease.
Our team of experts will help you with the process from start to finish.
We provide a straightforward, efficient and customer-focused service across all electricity services, including the following:
New Electricity Connections
Design and feasibility studies
Single phase 15kva domestic
Electricity Meter installation, re-location and disconnection
CT metering
Electricity Supply Disconnections
Electricity Supply Diversions
Electricity Supply Upgrades
Jointing (LV and HV)
Power Cable Installations (Mains & Service)
Site investigation and evaluations
Substation Installation and commissioning
Complete civils and groundworks packages
Cable laying and civils works
Temporary or permanent supplies
Earthing designs and studies
Power investigations of existing supplies and available capacity
Co-ordinate network designs and approvals
Evaluation of network point of connection (POC) quotes
Electric Vehicle Power Installations
Important Points To Consider
Each connection is unique, we cannot provide accurate time scales without collating all of the information from you first.
Experienced with various electricity connection sizes
Knowledge of DNO operations
Understanding of connection requirements and challenges
Insights into electrical grid complexity
Recognize DNO's role in power distribution
Realistic expectations for response times, service, and performance
Identifies potential challenges early,
streamlines the approval process and
minimises project delays
An average installation can take anywhere between 6 to 12 weeks, but these are only rough estimates.
The timescales could differ as we may need to apply for permits to excavate on public highways, obtain legal consents.
Where the point of connection is located will also determine costs.
Once we have all the information and established what is required to complete your connection, we are then able to give you an accurate timescale, price and expected date of completion.
Comprehensive initial documentation is crucial. It
establishes project scope, timelines and budgets.
Helpful Information Required To Progress Your Application
The full address of the property which requires a new connection.
A site & location plan/drawing of the property indicating where the meter is located or where you wish it to be installed. An accurate site drawing and Land Registry Plan would be beneficial
A letter of authority (LOA) to act on your behalf as the landowner/property owner